How is a compensation event quotation finalised and agreed?

1 Posts
1 Users
0 Reactions
45 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

A compensation event is implemented when the Project Manager accepts a Contractor’s quotation, the Project Manager makes their own assessment, or when the quotation is treated as having been accepted (when the Project Manager failed to respond to a reminder that they had not assessed the quotation).


 