Topic starter
A compensation event occurs if an instruction is not given by the date specified in the proposed instruction, or if the project manager notifies that it is not proceeding. According to clause 60.1(21), the contractor is reimbursed for any expenses incurred in creating a quote that doesn't go ahead.
Posted : 27/11/2025 3:32 pm