Topic starter
If the programme for the remaining work is affected by the compensation event, the Contractor includes the alterations to the Accepted Programme in the quotation. This is not a programme to ever to become an accepted programme but just to help the quotation be understood and assessed.
Posted : 28/11/2025 3:46 pm