When should a Project Manager assess a compensation event quotation?

1 Posts
1 Users
0 Reactions
39 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

When the Contractor has not submitted the quote within the time allowed, when the Project Manager decides the Contractor has not assessed the event correctly, when the contractor has not submitted a programme which the contract requires, or when the Contractor’s latest programme has not been accepted for one of the reasons stated in the contract.