We selected the Contractor partly on its methodology as expressed in its programming submission. But, under NEC, the programme is a ‘live’ document which can be changed providing it complies with the Scope. We accept that details and timings can chan

1 Posts
1 Users
0 Reactions
38 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

Our view is that the NEC is deficient in this respect. We suggest that, via a ‘Z’ clause, any reference to “Scope provided by the Contractor for its design” is changed to “Scope provided by the Contractor”. Then in the Contract Data, you have two entries, one for “Scope provided by the Contractor for its design” (as there is currently) and one “Scope provided by the Contractor for its methodology”. The methodology, expressed in sufficient detail, is then referenced from the second entry and it becomes a contractual obligation to follow that methodology.


 
Posted : 09/12/2025 11:09 am
Share: