Topic starter
The lack of early warning could be taken into account when assessing a subsequent compensation event (clause 63.7), and/or if a cost reimbursable type contract then any cost incurred due to the lack of early warning could become a reason for a Disallowed Cost (clause 11.2(25)).
Posted : 01/12/2025 1:42 pm