Notifications
Clear all
Topic starter
Anything that could increase the total of the Prices, delay Completion, delay meeting a Key Date or impair the performance of the works in use (or to simplify, anything that could impact time, cost or quality). An early warning may also be notified for any matter that could increase Contractor’s total cost.
Posted : 03/12/2025 10:27 am