Who should update the Early Warning Register?

1 Posts
1 Users
0 Reactions
25 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

This is the role of the named Project Manager or anyone whom they have formally delegated the power to do so. The use of a cloud-based system, such as Contract Bee, will only allow someone with administration rights to update the register.


 