Clause 50.5 requires the Project Manager to retain one quarter of the PWDD only if:
– there is no programme referenced in Contract Data Part two and
– the Contractor had not submitted its first programme or;
– the Contractor has submitted first programme but it has been not accepted (31.3) for the reason that it does not show ‘the information which the contract requires’.