Skip to content Skip to footer

Got a question about contract management?

Notifications
Clear all

If the Contractor has not submitted a programme, is an amount of money is retained from the Contractor?

1 Posts
1 Users
0 Reactions
43 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

Clause 50.5 requires the Project Manager to retain one quarter of the PWDD only if:

– there is no programme referenced in Contract Data Part two and
– the Contractor had not submitted its first programme or;
– the Contractor has submitted first programme but it has been not accepted (31.3) for the reason that it does not show ‘the information which the contract requires’.


 
Posted : 09/12/2025 11:20 am
Share: