Yes, if it no longer represents how the Contractor plans to carry out the works. Any revised activity schedule has to be accepted by the Project Manager. The only reasons for not accepting a revised activity schedule is that it is not in line with the programme, no longer reflects the total of the Prices, or the costs are not reasonably distributed (clause 55.4).