Skip to content Skip to footer

Got a question about contract management?

Notifications
Clear all

Under Option A, can the Contractor get paid based on the agreed ‘percentage completion’ of activities in the Activity Schedule?

1 Posts
1 Users
0 Reactions
34 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

No. Payment under option A is only on completion of activities.


 
Posted : 09/12/2025 11:43 am
Share: