Under Option C, does the Contractor get paid for correcting all the Defects?

1 Posts
1 Users
0 Reactions
69 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

No. There are two relevant bullets under 11.2(26) that would be a Disallowed Cost to do with defects:

– the cost of correcting Defects after Completion, and
– the cost of correcting Defects caused by the Contractor not complying with a constraint on how it is to Provide the Works stated in the Scope


 
Posted : 09/12/2025 3:06 pm