Can a Completion Date or sectional Completion Date ever be brought forward to an earlier date?

1 Posts
1 Users
0 Reactions
51 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

Only through acceleration in accordance with section 36 of the contract. Negative compensation events can NOT bring forward the Completion Date or a sectional Completion Date.


 