The maximum period between submissions would be the period stated in contract data 1 which for most projects would be either four weekly or monthly. The Project Manager can also instruct a revised programme at any stage, for which the Contractor would have to submit within the period for reply. The Contractor can also submit a revised programme whenever they choose.