The four stated reasons that the Project Manager can reject a programme for are that the Contractor’s plans they are showing are not practicable, it does not show the information the contract requires, it does not represent the Contractor’s plans realistically, or it does not comply with the Scope.
Posted : 15/12/2025 2:05 pm