Float as identified in clause 31.2 is commonly known as “total float” and is the amount an activity can slip before it will be affecting the critical path. An item with no float is commonly known as “critical” and will impact one of the contractual milestones if it is delayed.
Posted : 10/12/2025 11:39 am