It is the date when the Contractor is at that point in time anticipating achieving the status of Completion. This can be compared to the Completion Date to see if they are behind or ahead of schedule. A Contractor showing planned Completion beyond Completion Date will either be in delay for a reason of their own liability, or there may be compensation events yet to agree that may move the Completion Date in line with their planned Completion.