What is the Accepted Programme?

1 Posts
1 Users
0 Reactions
26 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

It is the programme identified in contract data or is the latest programme accepted by the Project Manager (which supersedes previous accepted programmes). A revised programme accepted by the Project Manager supersedes previous accepted programmes.


 