Topic starter
Not a term identified in the contract, but is the path of logic linked activities that if delayed will be impacting one of the contractual milestones on the project. Clause 31.2 identifies the requirement to show “float” on a programme issued for acceptance, and where float is zero then this would be what is classed as being critical.
Posted : 10/12/2025 11:59 am