Neil Earnshaw - "From what you’ve described, it sounds like a defect issue. If you've notified the defect of the subcontractor, if they fail to return to correct it within the period required by the contract, then you can assess the additional cost of having somebody else correct the defect. That's the simple mechanism."
Posted : 16/12/2025 1:58 pm