No, it is the Project Manager that certifies Completion (clause 30.2), So, based on the definition of Completion (11.2(2)), the Project Manager will decide if the Contractor has “corrected notified Defects which would have prevented the Client from using the works or Others from doing their work”. Note that it makes sense for the Contractor to know if a Defect may be considered as such when it is notified. Logically that would be included on the list of Defects but will need discussion between Supervisor and Project Manager. And the ultimate decision is with the Project Manager at Completion.