Skip to content Skip to footer

Got a question about contract management?

Notifications
Clear all

Does the Supervisor need to see Contractor’s designs as accepted by the Project Manager?

1 Posts
1 Users
0 Reactions
22 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

11.2(6): ‘A Defect is part of the works which is not in accordance with the Scope, or a part of the works designed by the Contractor which is not in accordance with the applicable law or the Contractor’s design which the Project Manager has accepted (clause 11.2(26)). The Supervisor therefore must be aware of those designs that have been accepted by the Project Manager. There is nowhere in the contract stating that the Project Manager should share those designs with the Supervisor, but practically speaking this will clearly need to happen to allow the Supervisor to fulfil their role.


 
Posted : 15/12/2025 2:41 pm
Share: