11.2(6): ‘A Defect is part of the works which is not in accordance with the Scope, or a part of the works designed by the Contractor which is not in accordance with the applicable law or the Contractor’s design which the Project Manager has accepted (clause 11.2(26)). The Supervisor therefore must be aware of those designs that have been accepted by the Project Manager. There is nowhere in the contract stating that the Project Manager should share those designs with the Supervisor, but practically speaking this will clearly need to happen to allow the Supervisor to fulfil their role.