Topic starter
Yes, if the test failure is notified by the Supervisor as a Defect. The Project Manager then assesses the cost incurred by the Client in repeating a test or inspection after a Defect is found. The Contractor pays the amount assessed (clause 41.6)
Posted : 15/12/2025 2:39 pm