Is there a clause under which the Supervisor confirms that a Defect has been properly corrected?

1 Posts
1 Users
0 Reactions
26 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

No (oddly), but it is clear that the Contractor and Supervisor will have to develop a process for this so that corrected Defects can be logged on a “list of Defects”.


 
Posted : 15/12/2025 3:31 pm