Are existing activity schedule rates or bill of quantity rates used to assess compensation events?

1 Posts
1 Users
0 Reactions
49 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

No, unless by agreement (and on a case-by-case basis). They should otherwise be based upon Defined Cost using the relevant schedule of cost components.


 
Posted : 28/11/2025 3:26 pm