If the works are carried out before a quotation is agreed, should this simply revert to being assessed as actual cost?

1 Posts
1 Users
0 Reactions
59 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 
[#45]

No, it should still be assessed based on forecast cost from the point at which the works were instructed, or for all other events when the Contractor notified the compensation event.


 
Posted : 28/11/2025 3:19 pm