Not all compensation events will have the opportunity of first notifying an early warning. For situations where the Project Manager decides the Contractor did not give an early warning of an event which the Contractor could have given then the Project Manager should state that fact in the instruction to the Contractor to submit a quotation (clause 61.5). They can then take this into account when assessing the compensation event quotation (clause 63.7).