No, which was why NEC4 changed the name from “Risk Register” to “Early Warning Register”. Traditional risk registers have numerous additional columns such as cost impact, programme impact, likelihood, severity, revised likelihood/severity post mitigation etc. The Early Warning Register only requires the description of the risk, and the action to be taken to avoid or mitigate the risk.