Is the Early Warning Register the same as a traditional risk register?

1 Posts
1 Users
0 Reactions
74 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 
[#59]

No, which was why NEC4 changed the name from “Risk Register” to “Early Warning Register”. Traditional risk registers have numerous additional columns such as cost impact, programme impact, likelihood, severity, revised likelihood/severity post mitigation etc. The Early Warning Register only requires the description of the risk, and the action to be taken to avoid or mitigate the risk.


 
Posted : 01/12/2025 10:09 am