Should potential costs be included within an Early Warning notification?

1 Posts
1 Users
0 Reactions
47 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 

There is no need to include costs as the intent is to consider matters and actions that could be taken to avoid or minimise the impact, rather than focusing on who’s liability is it and what will the cost be.