What happens if a Project Manager gives an instruction but does not notify a compensation event and the Contractor believes that it is a compensation event?

1 Posts
1 Users
0 Reactions
302 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 
[#31]

The Contractor should notify the compensation event under clause 61.3


 
Posted : 27/11/2025 3:05 pm