Is it necessary to show resources on a programme?

1 Posts
1 Users
0 Reactions
59 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 
[#108]

Not an obligation, unless such a requirement has been included within the Scope. It is however an obligation to state the principal equipment and resources that are needed to achieve each operation on the programme. Words are therefore obliged to be submitted with each programme to fulfil this requirement and help the Project Manager understand if they can accept that programme or not. With good planning software it is possible to show resources on the programme as a resource profile, which would probably negate the need for words and be much more of a practical management tool for both Parties.


 