What is terminal float?

1 Posts
1 Users
0 Reactions
58 Views
(@theoh)
Posts: 110
Reputable Member Moderator
Topic starter
 
[#106]

A common phrase used to refer to the difference between planned Completion and Completion Date when planned Completion is earlier than the Completion Date. This type of float is retained in the assessment of any compensation events i.e. is owned by the Contractor.


 